For this project we undertook a substantial installation focusing on the power and control systems for a telecommunications infrastructure. This work involved comprehensive electrical and cabling solutions tailored to the specific needs of the site, emphasizing reliability, safety, and future scalability.
Key Features
Main Power Distribution:
The project included installing a 120mm copper feed from the Teleport to the Groundwork Service Equipment (GWSE) H-Frame, ensuring robust power distribution for critical telecommunications equipment.
Control and Security Systems:
We installed conduits, boxes, and cabling for CCTV and access control systems, vital for securing the site and monitoring its operations effectively.
Infrastructure Enhancements:
The installation of check meters, RCD protection, distribution board enclosures, and MEN connections alighn with New Zealand standards, guaranteeing a compliant and efficient electrical setup.
Cable Management Solutions:
A cable tray was supplied and installed to facilitate power distribution from the trench to the Teleport GWSE Distribution Board, alongside the implementation of VSTX enclosures for enhanced system integrity.
Comprehensive Groundworks:
Installation of ducting in alignment with the site plan, ensuring seamless integration of the electrical infrastructure with the physical layout of the site.
Specialized Equipment and Materials:
The project utilized steel conduits for exposed areas, particularly along boundary fences, and incorporated advanced electrical components like 200amp DB for the GWSE H-Frame, adhering to the detailed specifications in the planning documents.